Principal Contractor duties under the Construction (Design and Management) Regulations 2015 (CDM 2015) are to plan, manage, monitor and coordinate health and safety during the construction phase of any project with more than one contractor. The client appoints the Principal Contractor in writing, and it prepares the construction phase plan, controls the site and works closely with the Principal Designer.
This guide is written for clients. It explains when you need a Principal Contractor, what the role covers, what you must do to support it, and how it differs from the Principal Contractor role under the Building Regulations. For support with the CDM arrangements on your own project, see our Construction Design and Management (CDM) Services. If you are new to the regulations, start with CDM Regulations 2015 explained and our guide to CDM duty holders.
What is a Principal Contractor under CDM 2015?
CDM 2015 sets out duties for clients, designers, the Principal Designer, contractors, the Principal Contractor and workers. The Principal Designer plans, manages and coordinates health and safety in the pre-construction phase. The Principal Contractor does the same for the construction phase, which runs from the start of construction work on the project to its completion.
The two roles work together. As we explain in our guide to the Principal Designer role, the Principal Designer passes the information it holds to the Principal Contractor so that the construction phase can be planned properly.
In practice the Principal Contractor is usually the main contractor, but the role is a legal appointment, not a job title. A contractor only becomes the Principal Contractor when the client appoints it to the role. Because the role carries real responsibility for the safety of everyone on and around the site, the contractor you appoint must have the skills, knowledge and experience for the job and, where it is an organisation, the organisational capability to deliver it. As the client, you must take reasonable steps to satisfy yourself that it does.
When must a Principal Contractor be appointed?
You must appoint a Principal Contractor whenever more than one contractor will work on the project, or it is reasonably foreseeable that more than one will, at any time. The test is the number of contractors. It has nothing to do with the size of the project or whether it has to be notified to the Health and Safety Executive (HSE). In practice most commercial projects meet it, because even a short fit-out usually involves a main contractor and at least one specialist trade contractor.
Three rules apply to the appointment:
- It must be in writing. A verbal understanding, or an assumption that the main contractor will take it on, is not enough.
- It must be made early. The appointment should be made as soon as practicable, and in any event before the construction phase begins.
- It must go to a contractor. Under CDM 2015, a contractor is anyone who directly employs or engages construction workers, or who manages construction work.
What does a Principal Contractor do?
The core duty is set out in regulation 13. The Principal Contractor must plan, manage and monitor the construction phase, and coordinate health and safety, so that the work is carried out without risks to health or safety so far as is reasonably practicable. In practice, the Principal Contractor duties break down as follows.
| DUTY | WHAT IT INVOLVES | CDM 2015 |
| Construction phase plan | Draw up the plan during the pre-construction phase, before the site is set up, then review, update and revise it throughout the project. | Reg 12(1), 12(4) |
| Planning and coordination | Apply the general principles of prevention when planning the work and estimating how long it will take, and organise cooperation between contractors, including those working one after another on the same site. | Reg 13(1) to 13(3) |
| Site induction | Make sure every worker receives a suitable, site-specific induction. | Reg 13(4)(a) |
| Site security | Take the necessary steps to prevent unauthorised access to the site. | Reg 13(4)(b) |
| Welfare facilities | Provide welfare facilities that meet Schedule 2 (toilets, washing facilities, drinking water, changing and rest areas) throughout the construction phase. | Reg 13(4)(c), Sch 2 |
| Working with the Principal Designer | Liaise with the Principal Designer for the length of its appointment and share information relevant to health and safety. | Reg 13(5) |
| Consulting workers | Set up arrangements for workers to cooperate on health, safety and welfare, consult them or their representatives in good time, and let them see relevant information. | Reg 14 |
| Health and safety file | Give the Principal Designer information for the health and safety file. If the Principal Designer’s appointment ends early, take over the file, keep it up to date and hand it to the client at the end. | Reg 12(7) to 12(10) |
The Principal Contractor also keeps its ordinary duties as a contractor, including making sure that the contractors and workers it brings onto the project are competent for their work.

What must the client do to support the Principal Contractor?
Appointing a Principal Contractor does not hand over your own duties. CDM 2015 makes commercial clients responsible for the arrangements the rest of the project depends on, and several of them decide how well the Principal Contractor can do its job.
- Allow enough time and resources. You must make suitable arrangements for managing the project, including allocating sufficient time and other resources. A programme that leaves no room to plan the construction phase makes the Principal Contractor’s job harder from day one.
- Provide pre-construction information. As soon as practicable, give every designer and contractor who is appointed, or being considered for appointment, the information you hold or can reasonably obtain about the project, the site and any existing structures. Contractors price and plan around it, so gaps here tend to come back later as cost and programme problems.
- Make sure the construction phase plan is in place before work starts. You must ensure the Principal Contractor draws up the plan before the construction phase begins. It is reasonable to ask to see it before you let work start on site.
- Make sure welfare facilities are provided for the whole of the construction work.
- Check that the duties are being carried out. You must take reasonable steps to ensure that the Principal Designer and the Principal Contractor carry out their duties, and keep your own arrangements under review for the life of the project.
- Notify HSE where required. A project is notifiable if construction work is planned to last longer than 30 working days and have more than 20 workers on site at the same time at any point, or to exceed 500 person days. Notification is the client’s duty, using form F10, and a copy must be displayed in the site office.

What happens if the client does not appoint a Principal Contractor?
The duties do not disappear. If your project needs a Principal Contractor and you do not appoint one, regulation 5(4) makes you, the client, responsible for carrying out the Principal Contractor’s duties under regulations 12 to 14 yourself. For most commercial clients that would mean taking control of the construction phase, including the construction phase plan, site inductions, security and welfare, without the people or systems a contractor has to do it.
Domestic clients, meaning people having work done on their own home that is not connected with a business, are treated differently. If a domestic client does not make the appointment, the contractor in control of the construction phase becomes the Principal Contractor.
Is the CDM Principal Contractor the same as the Building Regulations Principal Contractor?
No. They share a name but cover different duties, and on a project in England you may need both.
Since 1 October 2023, building work in England has been subject to a dutyholder and competence regime in Part 2A of the Building Regulations 2010, added by the Building Regulations etc. (Amendment) (England) Regulations 2023 as part of the reforms that followed the Building Safety Act 2022. It creates its own client, designer, Principal Designer, contractor and Principal Contractor roles.
| The CDM 2015 Principal Contractor | The Building Regulations Principal Contractor |
|---|---|
| Manages health and safety during the construction phase. CDM 2015 applies across Great Britain. | Plans, manages and monitors the building work so that it complies with the Building Regulations, and confirms at completion that it has fulfilled its duties. |
Where more than one contractor is involved, the client must appoint a Building Regulations Principal Contractor in writing. Instead, the client can certify in writing that the CDM Principal Contractor is also treated as the Principal Contractor under the Building Regulations, provided it is competent for both roles. If the client does neither, it must carry out the Building Regulations Principal Contractor’s duties itself.
On most commercial projects the same contractor fills both roles. What matters is that the appointment documents say so clearly, and that the contractor is competent for both.
How CCM can help
CCM works on the client side. We help clients set their projects up so the Principal Contractor can do its job well, and we keep a close eye on delivery once work starts. Depending on our appointment, that can include:
- explaining your duties as a client under CDM 2015 at the start of the project
- preparing and issuing pre-construction information
- preparing a project risk register with supporting guidance
- checking the competence of tendering contractors before you appoint a Principal Contractor
- reviewing the construction phase plan before work starts on site
- monitoring progress on site and following up actions through our On-Site Monitoring and Inspections service
- coordinating design risk through our CDM Services, and acting as Principal Designer on suitable projects
To talk through the CDM arrangements for your project, get in touch with our team.
Frequently asked questions
Yes, if the same organisation is both a designer and a contractor and has the skills, knowledge, experience and organisational capability for both roles. This is common on design and build projects. Both appointments must still be made in writing.
It depends on the number of contractors, not the size of the project. If more than one contractor will work on the project at any time, you need one, even if the project does not have to be notified to HSE.
The Principal Contractor, on any project with more than one contractor. On a single-contractor project, the contractor writes it. Either way, as the client you must make sure it is drawn up before the construction phase begins.
The Principal Designer prepares and updates it, using information the Principal Contractor provides. If the Principal Designer’s appointment ends before the project does, the file passes to the Principal Contractor, who keeps it up to date and hands it to you at the end. You should keep it available for anyone who carries out future work on the building.
No. You either appoint a Principal Contractor under the Building Regulations in writing, or certify in writing that your CDM Principal Contractor is also treated as the Building Regulations Principal Contractor.