Under the Construction (Design and Management) Regulations 2015 (CDM 2015), the duty holders are the client, designers, the Principal Designer, contractors, the Principal Contractor and workers. Domestic clients are covered too, but their duties pass to others. Each duty holder has legal responsibilities for managing health and safety on a construction project.
Knowing who holds each role, and what each one must do, is the quickest way to see whether a project is set up properly. This guide explains each duty holder in turn, how the roles work together from design to handover, and what clients should check. For an overview of the regulations themselves, read our guide to the CDM Regulations 2015. If you need support on a project, our CDM Services cover client advice and Principal Designer appointments.
Who Are the Duty Holders Under CDM 2015?
| Duty holder | Who it is | When they are involved | Key duties |
| Client | The organisation or person the project is carried out for | From the decision to go ahead, and after handover while they hold an interest in the building | Suitable arrangements, time and resources, appointing the right people, pre-construction information |
| Domestic client | Someone having work done on their own home, or a family member’s, not in connection with a business | Throughout the project | Their client duties normally pass to the contractor, the Principal Contractor or, by written agreement, the Principal Designer |
| Designer | Any business that prepares or modifies a design, drawing, specification or bill of quantities, or arranges for or instructs anyone under its control to do so | Mainly during design, and whenever the design changes | Eliminating, reducing or controlling foreseeable risks through the design, and providing information about remaining risks |
| Principal Designer | A designer with control over the pre-construction phase, appointed in writing by the client | Where there is, or will foreseeably be, more than one contractor; appointed as soon as practicable | Planning, managing, monitoring and coordinating health and safety before construction, and preparing the health and safety file |
| Contractor | Any business that carries out, manages or controls construction work | From appointment to completion of their work | Planning, managing and monitoring their own work, and supervising and informing their workers |
| Principal Contractor | A contractor appointed in writing by the client to control the construction phase | Where there is, or will foreseeably be, more than one contractor; appointed as soon as practicable and before construction starts | The construction phase plan, coordinating contractors, site inductions, site security and welfare |
| Worker | Anyone carrying out construction work, from labourers and trades to supervisors | Whenever they are on site | Taking care of their own and others’ health and safety, cooperating, and reporting anything likely to endanger health and safety |
What Does the Client Do Under CDM 2015?
The client is the organisation or person the project is carried out for. A commercial client is anyone having construction work done in connection with a business, whether or not it makes a profit. That includes developers, landlords and organisations fitting out their own premises.
The client sits at the top of the chain because it controls the budget, the programme and the appointments. Its duties include making suitable arrangements for the project, allowing sufficient time and resources, appointing designers and contractors with the right skills and experience, providing pre-construction information and, where more than one contractor is involved, appointing a Principal Designer and a Principal Contractor in writing. The client must also make sure that welfare facilities are provided, that there is a construction phase plan and, where needed, a health and safety file, that the Principal Designer and Principal Contractor carry out their duties, and that the Health and Safety Executive (HSE) is notified if the project is notifiable. We set out the client’s duties in full in our guide to the CDM Regulations 2015.
A client can also take on another role without realising it. A commercial client that prepares or changes a design is a designer for that work. A commercial client that carries out, manages or controls construction work itself, for example by directing trade contractors or using its own staff to do the work, also takes on contractor duties for that work. Our guide to construction procurement explains how the procurement route shapes who does what.
What about domestic clients?
A domestic client is someone having work done on their own home, or a family member’s, not in connection with a business. They do not have to carry out the client duties themselves. Those pass to the contractor where there is only one, to the Principal Contractor where there is more than one, or to the Principal Designer if they agree this in writing. If a domestic client does not make the appointments, the designer in control of the pre-construction phase becomes the Principal Designer, and the contractor in control of the construction phase becomes the Principal Contractor.
What Do Designers Do Under CDM 2015?
“Designer” covers far more than architects. Under CDM 2015, a designer is anyone who, in the course of a business, prepares or modifies a design for a structure, or arranges for someone under their control to do so. Design includes drawings, design details, specifications, bills of quantities and calculations. So architects, structural and building services engineers, quantity surveyors, interior designers, specifiers and contractors who design part of the works can all be designers.

A designer must:
- Not start work unless satisfied that the client is aware of its duties under CDM 2015
- Take account of the general principles of prevention and the pre-construction information to eliminate, so far as reasonably practicable, foreseeable risks to anyone carrying out or affected by construction work, maintaining or cleaning the structure, or using a structure designed as a workplace
- Where a risk cannot be eliminated, reduce or control it through the design and give information about it to the Principal Designer
- Make sure appropriate information goes into the health and safety file
- Provide enough information with the design to help the client, other designers and contractors meet their duties
In practice, this means thinking about how something will be built and maintained while it can still be changed on paper. Safe access for cleaning high-level glazing, the weight and handling of materials, and the routing of services in an occupied building are all design decisions with health and safety consequences.
Where CCM provides Architectural Design on a project, we have designer duties under CDM 2015 for that work.
What Does the Principal Designer Do?
The Principal Designer must be a designer with control over the pre-construction phase, appointed in writing by the client where there is more than one contractor, or it is reasonably foreseeable that there will be. It is often the lead designer, or a specialist that is itself a designer with control over the pre-construction phase, and it can be an organisation or an individual.
The Principal Designer must plan, manage, monitor and coordinate health and safety during the pre-construction phase. That includes identifying and eliminating or controlling foreseeable risks, making sure all designers carry out their duties, and making sure everyone working on the pre-construction phase cooperates. The Principal Designer also helps the client provide pre-construction information, passes it to designers and contractors, liaises with the Principal Contractor, and prepares and updates the health and safety file.
The pre-construction phase can continue during construction, because design often does. The Principal Designer’s role lasts for the length of its appointment, and, if that appointment ends before the project does, the health and safety file passes to the Principal Contractor.
What Do Contractors Do Under CDM 2015?
A contractor is any business that carries out, manages or controls construction work. That includes main contractors, trade and specialist contractors, sole traders and, where it manages the work itself, a commercial client. Every contractor has duties, whatever the size of the job.

A contractor must:
- Not start work unless satisfied that the client is aware of its duties
- Plan, manage and monitor its own work and the work of anyone under its control, so it is carried out without risks to health and safety, so far as reasonably practicable
- Where there is more than one contractor, follow any directions from the Principal Designer or Principal Contractor and the relevant parts of the construction phase plan
- Only employ or appoint people who have, or are gaining, the skills, knowledge, training and experience for their tasks
- Give its workers appropriate supervision, instructions and information, including a site induction where the Principal Contractor has not provided one
- Not start work on site unless reasonable steps have been taken to prevent unauthorised access, and make sure, so far as reasonably practicable, that its workers have the required welfare facilities
Where there is only one contractor, that contractor must also draw up the construction phase plan before setting up the site.
What Does the Principal Contractor Do?
The Principal Contractor is a contractor appointed in writing by the client to control the construction phase where there is more than one contractor, or it is reasonably foreseeable that there will be. It must be appointed as soon as practicable, and in any event before the construction phase begins.
The Principal Contractor must plan, manage, monitor and coordinate health and safety during the construction phase. In practice, it:
- Draws up the construction phase plan before the site is set up, and keeps it under review
- Organises cooperation between contractors and coordinates how they meet their health and safety duties
- Makes sure there is a suitable site induction, that the necessary steps are taken to prevent unauthorised access to the site and that welfare facilities are provided throughout the works
- Consults and engages with workers on health, safety and welfare
- Liaises with the Principal Designer and provides information for the health and safety file
What Are Workers’ Duties Under CDM 2015?
Workers are the people who carry out construction work, including trades such as electricians, plumbers, scaffolders, decorators and labourers, and supervisors such as foremen and chargehands. Workers must take care of their own health and safety and that of others who may be affected by their work. They must cooperate with their employer and the other duty holders, and report anything they are aware of that is likely to endanger their own or others’ health and safety. HSE also expects workers to carry out only work they have the skills and training for, and to follow the site rules. The Principal Contractor, in turn, must consult workers or their representatives on matters that affect their health, safety and welfare.
How Do the CDM Duty Holders Work Together?
CDM 2015 works when information moves between the duty holders at the right time. Everyone with a duty must cooperate with others working on or near the project, and any information or instruction they give must be clear and provided as soon as practicable. The table below shows how the roles connect through a typical project.
| Stage | Who leads | What passes between them |
| Brief and early design | Client, Principal Designer, designers | The client appoints the Principal Designer as early as possible and provides pre-construction information; designers identify risks; the Principal Designer coordinates them and shares the information |
| Appointing contractors | Client | The client checks the competence of contractors and appoints the Principal Contractor in writing |
| Before work starts | Principal Contractor, Principal Designer | The Principal Designer passes relevant information to the Principal Contractor, which draws up the construction phase plan |
| Construction | Principal Contractor, contractors, workers | Contractors follow the plan and the Principal Contractor’s directions; the Principal Designer and Principal Contractor keep liaising while design continues |
| Handover | Principal Designer (or Principal Contractor), client | The Principal Designer, or the Principal Contractor if the Principal Designer’s appointment has ended, hands the completed health and safety file to the client to keep for future work |
Can one organisation hold more than one role?
Yes, as long as it has the skills, knowledge, experience and organisational capability for each role. A design and build contractor, for example, may be appointed as Principal Contractor and, if it is a designer with control over the pre-construction phase, as Principal Designer too. A commercial client with its own design or project team may also be a designer or a contractor for the work it carries out.
What if the client does not appoint a Principal Designer or Principal Contractor?
A commercial client that fails to make either appointment must carry out those duties itself, which is a significant legal responsibility to take on by default. Our guide to the CDM Regulations 2015 covers the appointment rules in full.
How CCM Supports Clients With CDM Duty Holder Roles
CCM provides CDM consultant and Principal Designer services for commercial, retail, and electric vehicle (EV) and energy projects across Great Britain, from our base in Cheltenham. Depending on what your project needs, we can:
- Help you work out which duty holder roles apply, which appointments you need and what information is required
- Act as Principal Designer under a written appointment, coordinating designers and health and safety in the pre-construction phase
- Help bring together pre-construction information and coordinate designers on foreseeable design risks
- Liaise with the Principal Contractor about design risks that need managing during construction
Appointing CCM does not take your client duties away from you. The written appointment sets out exactly what we have accepted, and every duty holder remains responsible for its own duties under CDM 2015. To discuss a project, see our CDM Services or contact us.
Frequently Asked Questions
CDM 2015 does not name five duty holders. The phrase usually means the client, the designer, the Principal Designer, the contractor and the Principal Contractor. HSE lists seven roles in total, adding workers and domestic clients, whose client duties pass to others.
Where there is more than one contractor, the Principal Contractor plans, manages, monitors and coordinates the construction phase. Each contractor remains responsible for its own work and workers, and the client must make sure suitable arrangements are in place throughout. On a single-contractor project, that contractor manages the construction phase.
Anyone with a legal duty under CDM 2015. That covers clients, designers, the Principal Designer, contractors, the Principal Contractor and workers. One person or organisation can hold more than one role on the same project.
Yes. CDM 2015 applies to all construction work, so every contractor must plan, manage and monitor its own work, check the client is aware of its duties and look after its workers. A sole contractor must also draw up a construction phase plan before setting up the site.